The Loan for Paks is being Prepaid

Date: 02.19.2020

It is close to the ninety billion forints that the Hungarian side has drawn from the Russian credit line for the Paks II investment. However, most of the money used has already been repaid by the Hungarian government, meaning that no interest will have to be paid.


The Magyar Nemzet reports, that State Secretary of the Ministry of Finance presented recent data on how much the Hungarian side has withdrawn from the Russian credit line for the investment to maintain the capacity of the Paks Nuclear Power Plant, the Paks II project.

András Tállai, responding to a parliamentary question, said that according to the international credit agreement between the Russian Federation and Hungary, a total of EUR 239 million (about HUF 78.8 billion) has been drawn down by the Hungarian party since the opening of the credit line for NPP construction, most of the amount has already been prepaid.

So far, the Hungarian government has paid a total of EUR 1,821 million (HUF 600 million) within the time limits specified in the contract. The 2014 intergovernmental agreement includes a credit line of EUR 10 billion (HUF 3,300 billion).


Latest News

Paks II: Approval of Soil Preparation Work Received in Brussels
Date: 05.17.2020

The European Commission has approved the planned amendment of the government decree regulating the site preparation works related to Paks II project. It means that – after submission of the construction permit – the licensing process can start, which can be continued by earthworks at the beginning of next year as well – informed János Süli, Paks, Minister for Paks II Investment. He said the pandemic situation made it difficult, but not impossible, to continue the work on Paks II project.

Read more


The Loan for Paks is being Prepaid
Date: 02.19.2020

It is close to the ninety billion forints that the Hungarian side has drawn from the Russian credit line for the Paks II investment. However, most of the money used has already been repaid by the Hungarian government, meaning that no interest will have to be paid.

Read more


Kalocsa and its Region can be a Winner of the Paks II. Investment
Date: 02.24.2020

János Süli, minister without portfolio, is also committed to make the most of the development opportunities offered by the investment for Kalocsa and its region, it was told during a forum, organized by Club of Entrepreneurs of Kalocsa.

Read more


Süli: New Paks Blocks are Going to be World-class As Well
Date: 02.17.2020

Minister János Süli said at a corporate executive forum organized by the Joint Venture Association and its partners, that the new units will bring back the investment and generate profits.

Read more


New Opportunities for Domestic Enterprises in Paks II Project
Date: 01.22.2020

As KaloHírek reports that domestic entrepreneurs can join more and more tasks in Paks II project. Minister János Süli said that the construction of the service buildings and the regional development also offer opportunities. Paks II Zrt. on June 30, 2020 will submit the most complex application ‒ the one on the construction licence ‒ to the National Atomic Energy Authority.

Read more


Sign Up for Newsletter

Don’t miss any business possibility regarding the construction of the nuclear power plant: sing up for the newsletter and stay updated!
I agree to the terms of use.
Imprint
Company Hype Kft.
 
Head Office
2161 Csomád,
Cseresznyés u. 1/A.
Contacts
00 (36) 1 920 0805
info@atombusiness.hu